Fiber Project Updates

Fiber Project Updates

Our teams have been hard at work planning and designing our Fiber to the Premise expansion projects! Read below for details on each project and check back for more updates.

Forsyth • ConnectMT »

Forsyth FTTP build will reach approximately 965 locations in Forsyth, Montana. Construction is scheduled to start in Spring 2024, without any significant delays due to weather.

Range’s partner Vantage Point will be contacting customers to schedule site visits starting late January 2024.


Colstrip • ConnectMT »

Colstrip FTTP build will reach approximately 615 locations in Colstrip, Montana. Construction is scheduled to start in Spring 2024, without any significant delays due to weather.

Range’s partner Vantage Point will be contacting customers to schedule site visits starting in Spring 2024.


West River Rd »

West River Rd FTTP build will reach approximately 130 locations in the Worland, Wyoming area. Construction is anticipated in 2024, without any significant delays due to weather.


Weber Mesa »

Weber Mesa FTTP build will reach approximately 75 locations in the Baggs, Wyoming area. Construction is anticipated in 2024, without any significant delays due to weather.


Moorcroft »

Moorcroft FTTP build will reach approximately 221 locations in the Moorcroft, Wyoming area. Construction is anticipated in 2024, without any significant delays due to weather.


Sundance East »

Sundance East FTTP build will reach approximately 121 locations in the Sundance, Wyoming area. Construction is anticipated in 2024, without any significant delays due to weather.


North Worland »

North Worland FTTP build will reach approximately 291 locations in the Worland, Wyoming area. Construction has been completed. More information on connecting customers to the network will be arriving soon.


Town of Broadus »

Town of Broadus FTTP build will reach approximately 323 locations in Broadus, Montana. Construction has been completed. More information on connecting customers to the network will be arriving soon.

 

COMPLETED PROJECTS

 

Custer Highlands »

Custer Highlands FTTP build will reach approximately 186 locations in Newcastle, Wyoming. Construction has been completed. Customers have been connected.


Carpenter »

Carpenter FTTP build will reach approximately 169 locations in the Carpenter, Wyoming area. Construction has been completed. Customers have been connected.


North Broadus Phase 4 & 5 »

North Broadus Phase 4 & 5 FTTP builds will reach approximately 47 locations in the Broadus, Montana area. Construction has been completed. Customers have been connected.


Ucross/Dow Prong »

Ucross/Dow Prong FTTP build will reach approximately 77 locations in the Ucross, Wyoming area. Construction has been completed. Customers have been connected.


Dinwoody East Aerial »

Dinwoody East Aerial FTTP build will reach approximately 22 locations in the Dubois, Wyoming area. An update coming soon.


Down Rivers/Highway 13 »

Down Rivers/Highway 13 FTTP build will reach approximately 19 locations in Baggs, Wyoming, and Craig, Colorado. Construction has been completed. Customers have been connected.


Timberline »

Timberline FTTP build will reach several homes in the Dubois, Wyoming area. Construction has been completed. Customers have been connected.