Our Network Engineering teams have been hard at work planning and designing our Fiber to the Premise expansion projects for this spring! As soon as this snow melts, we will be building to 531 homes in 6 communities across our serving area. Read along below for details on each project and check back for more updates.


Custer Highlands »

Our Custer Highlands FTTP build will be reaching 186 homes in Newcastle, Wyoming. Construction is scheduled to start in mid-April and last through June 30th, without any significant delays due to weather.


Carpenter »

Our Carpenter FTTP build will be reaching 169 homes in the Carpenter, Wyoming area. Construction began in April and will last through May 31st, without any significant delays due to weather.


North Broadus Phase 4 & 5 »

Our North Broadus Phase 4 & 5 FTTP builds will be reaching 47 homes in Broadus, Montana. Construction is delayed due to sage grouse restrictions and is scheduled to start on July 10th and last through September 15th, without any significant delays due to weather.


Ucross/Dow Prong »

Our Ucross/Dow Prong FTTP build will be reaching 77 locations in the Ucross, Wyoming area. Construction is scheduled to start in late April and last through June 30th, without any significant delays due to weather.


Dinwoody East Aerial »

Our Dinwoody East Aerial FTTP build will be reaching 22 homes in the Dubois, Wyoming area. Construction is underway and is scheduled to last through May 31st, without any significant delays due to weather.


Down Rivers/Highway 13 »

Our Down Rivers/Highway 13 FTTP build will be reaching 19 homes in Baggs, Wyoming and Craig, CO. Construction is scheduled to start in the spring and last through June 9th, without any significant delays due to weather.